Community update - Construction

Thank you for your patience as we work to deliver The Parks Red Hill. We hope you have been enjoying the recently opened central park and look forward to delivering the additional pocket parks over the remainder of the development.


Construction update – Stage 1


Stockland - Terraces Update

As you will have seen, work is progressing well on Stage 1 of the Terraces (Stockland), with all Terraces now sold out. The first Terrace homes in stage 1 will be completed in the first half of 2022.


Stockland – Vacant Land Blocks

With settlement having occurred on the vacant land blocks across the site, these buyers are commencing their individual home construction.


We would like to remind members of the community that responsibility and management for these individual home builds now rests with the new owners of each block and any concerns should be directed to them or their builders directly.


Construction update – Stage 2


Stockland is now preparing to release Stage 2 of its Terrace homes to the market, commencing with a VIP preview this coming Friday 4 June. This stage will include the construction of 42 Terraces.


The Residences (DOMA)

DOMA is working through final authority approvals ahead of commencing work on the six apartment buildings comprising 135 apartments in accordance with the Development Approval.


Subject to final approvals being granted, DOMA is aiming to commence construction in the coming months on the Eastern apartment blocks. This will involve closure of some of the roads around the apartment blocks to enable construction. We will provide a further notice once a firm commencement date is known.


The remainder of the apartment blocks (Residences Stage 2) is forecast to commence shortly after.


DOMA and Stockland plan to hold a community drop in session at the Red Hill shops in coming weeks to answer any questions on the construction process. Details will be communicated shortly regarding this session.


Upcoming pedestrian footpath closure – Beagle St


As we move into the next significant phase of construction, and with an increase of construction traffic, it will be necessary to close the eastern pedestrian footpath that runs between Beagle Street and the project site. This closure is required to ensure pedestrian safety is maintained. This footpath is proposed to be closed on 11 June 2021. It will be reassessed once Stage 1 Terrace Construction and vacant block construction are complete.


The western footpath will remain open in the short term but will be need to be closed prior to apartment construction commencement. We will provide a further notice advising of its closure.


We apologise for any inconvenience caused by this temporary closure, however the health and wellbeing of residents are Stockland and DOMA’s top priority.