DATES FOR IMPORTANT ROAD CLOSURES NOTICE – ENDEAVOUR ST/CYGNET CR

Following on from BMD's correspondence on 08/07/2020 regarding the proposed road closure to Endeavour St / Cygent Crescent, we have now received approval for the Temporary Traffic Management Plan. 

We will be commencing on stage 1 of the works on 27/07/2020

Stage 1 of these works include: 

  • Scope:

  • Temporary pedestrian path constructed

  • Water main road crossings

  • Stormwater main crossings


  • Duration: Approx. 2-3 Weeks

  • Impact: Road Closed. Temporary pedestrian path open

  • Once the crossings are completed, we will re-open the road for general public 

We will be provide an update prior to commencement of stage 2 of the works. This will involve the removal of road surfaces and replacement of kerbs and asphalt.

Local pedestrian / traffic changes will include:

  • Pedestrian Footpath

A temporary footpath linking Endeavour St and Monaro Cr will be provided during the road closure periods. 

  • Vehicular Traffic Detour

A detour directing vehicles to alternative routes will be set up in line with the approved TTM. 

  • Norfolk St

Norfolk St to remain closed to both pedestrian and vehicular traffic until the end of August 20. 

Access will remain to all existing driveways during this time.

BMD understand that this may be inconvenience and hopes to work together with you in a professional and amicable manner for the long-term improvement of your neighbourhood.





Your patience, and co-operation is greatly appreciated while the works are under way. If you have any questions about these works or would like more information, please do not hesitate to contact BMD or please contact Stockland Community Engagement Manager, Fiona Benson, on 0407 294 620 or at fiona@fjpartners.com.au


Download a copy of the notice (PDF)

Red Hill Precinct Development - Endeavou

0 views

© 2018 Stockland and DOMA
 

COMMUNITY ENQUIRIES
1800 909 773

info@theparksredhillcommunity.com.au

Disclaimer: This website is supplied for the purpose of providing an impression of The Parks, Red Hill and the approximate location of existing and proposed third party infrastructure, facilities, amenities, services and destinations, and is not intended to be used for any other purpose. All details, images and statements are based on the intention of, and information available to, Stockland and DOMA as at the time of publication (November 2018) and may change due to future circumstances.