December site update and Christmas shutdown

Works completed over prior month(s)


Remediation works

  • We are approximately 70 - 80% through the remediation works onsite and tracking well on our approved program.

  • We are currently remediating the western section of the side (La Perouse) with the majority of the other areas having now been remediated.

  • We anticipate that the majority will be complete by January 2020 with roads / verge works complete by late February 2020.

Civil works

  • We have commenced our cut / fill / compact operations to the eastern section of the site.

  • Temporary footpaths installed

  1. Monaro Crescent

  2. Cygnet Crescent


Works ahead over December 2019

  • Complete the remediation of the western section of the site.

  • Continue with civil works to the eastern section (Monaro Crescent)

  • Undertake stormwater tank works (central area – opposite the shops)

  • Undertake hydraulics works in the eastern area

  • New road box out (Cimba Lane & Aviemore Lane) – connection to Monaro Crescent


Christmas Shut Down Period

  • The site will be closed between 18thDec 2019 to 06thJanuary 2020. Our toll free community hotline and email will continue to be monitored during this time.


Traffic / Pedestrian

  • Monaro road closures between Discovery St and Cygnet Crescent will continue

  • Temporary footpaths in place for

  1. Monaro Crescent

  2. Cygnet Crescent


Community / Environmental / WHS


Stakeholder Communications

  • Introduction of weekly public notices of forecast works on site. These 'traffic light' reports provide surrounding residents and the wider community with more information and timely updates on work forecast to be carried out on the site.

  • The reports contain a more detailed description on daily project activities for the coming fortnight.

  • Key project changes including traffic management updates to be include on the Notice Board outside the SupaExpress and posted around the site

Dust Management

  • Polymer coating of all exposed site areas where there are no current works

  • Water spray dust suppression in work areas


Vibration Monitoring

  • Vibration monitors are operational along the project site boundary to ensure compliance with authority guidelines.


Noise Management

  • All noisy activities to be managed in line with the TCCS guidelines


Truck haul routes

  • Dalrymple St is not to be used as a trucking haul routeAll haulage to be carried out between the hours of 0700hrs and 1700hrs.

  • No haulage to be conducted during the school drop off and pick up hours, 0800hrs to 0900hrs and 1500hrs to 1600hrs


Drone Surveys

  • Drone flights are being used for daily site surveys (volumetric calculations, progress photos, stockpile management and progress tracking). These are used as part of the remediation record keeping.

  • Drone flights are managed in line with CASA guidelines.


We wish you a safe and happy holiday period and thank you again for your patience in 2019 as we progress this project.

© 2018 Stockland and DOMA
 

COMMUNITY ENQUIRIES
1800 909 773

info@theparksredhillcommunity.com.au

Disclaimer: This website is supplied for the purpose of providing an impression of The Parks, Red Hill and the approximate location of existing and proposed third party infrastructure, facilities, amenities, services and destinations, and is not intended to be used for any other purpose. All details, images and statements are based on the intention of, and information available to, Stockland and DOMA as at the time of publication (November 2018) and may change due to future circumstances.