Works completed over prior month(s) (February 2020)

  • ACM remediation works - Lot 8 - Lot 6 Verges along Cygnet Cr & Norfolk St - Lot 4 Verges along Cygnet Ct & Walter Hood Lane

  • Earthworks - Level 1 fill in Lot 6 - Level 1 Fill in Lot 8 - Level 1 Fill in Lot 4

  • Civil Works - Hydraulics – Sewer Works in Lots 1 & 3 - Hydraulics – Stormwater Works in Lot 1 - Hydraulics – Water Works in Lot 1 - Stormwater Tank walls and roof


Works ahead over next month (March 2020)

  • ACM remediation works - Lot 8 - Lot 2 - Lot 7 - Trench chasing in Lot 7 - Trench chasing in Lot 2 - Trench chasing in Lot 8 - Lot 7 Verges along Cygnet Cr & Norfolk Rd

  • Earthworks - Level 1 fill in Lot 4 - Level 1 fill in Lot 8 - Level 1 fill in Lot 7 - Level 1 fill in Lot 2 - General earthworks in Lot 5 - Excess material removal from site.

  • Civil Works - Hydraulics – Sewer Works in Lot 4 & 8 - Hydraulics – Stormwater Lot 8 - Hydraulics – Water Lots 1, 2 & 8 - Common Services Trenches – Lots, 1, 2 & 8 - Stormwater Tank finishing works

  • Landscaping - Preparation works in Lots 4 & 5


Potential Changes to Traffic Pedestrian Changes etc

  • Monaro road closure between Discovery St and Cygnet Crescent – notice issued

  • Discovery Street partial closure – notice issued

  • Norfolk St closed – notice issued

  • Temporary footpaths - installed - Monaro Crescent - Cygnet Crescent - Endeavour St


Community / Environmental / WHS

  • Stakeholder Notice Board - Notice board to advise Red Hill community of project updates to be maintained - Key project changes including traffic management updates to be include on the Notice Board - Undertake internal dilapidation surveys for properties bordering Lots 4, 6, & 7 - Structural Inspections to 2 no. properties on Beagle St

  • Dust Management - Water spray dust suppression in work areas

  • Vibration Monitoring - Vibration monitoring ongoing

  • Stockpile management - Water spray dust suppression for stockpiles in use

  • Noise Management - All noisy activities to be managed in line with the TCCS guidelines - Prior notification of residents of excessive noise activities to be made

  • Truck haul routes - Dalrymple St is not being used as trucking haul route - All haulage to be carried out between the hours of 0700hrs and 1700hrs. No haulage to be conducted during the school drop off and pick up hours, 0800hrs to 0900hrs and 1500hrs to 1600hrs

  • UAV Surveys - Drone flights used only for daily site surveys (volumetric calculations, progress photos, stockpile management and progress tracking) - Drone flight managed in line with CASA guidelines


Thank you again for your patience in 2020 as we progress this project.

4 views

© 2018 Stockland and DOMA
 

COMMUNITY ENQUIRIES
1800 909 773

info@theparksredhillcommunity.com.au

Disclaimer: This website is supplied for the purpose of providing an impression of The Parks, Red Hill and the approximate location of existing and proposed third party infrastructure, facilities, amenities, services and destinations, and is not intended to be used for any other purpose. All details, images and statements are based on the intention of, and information available to, Stockland and DOMA as at the time of publication (November 2018) and may change due to future circumstances.