March/April works update

Works completed over prior month(s) (March 2020)


  • ACM remediation works - Lot 2 - Lot 7 - Lot 7 Verges along Cygnet Cr & Norfolk St - Lot 5 Verges along Lady Nelson Place

  • Earthworks - Level 1 fill in Lot 7 (North Section) - Level 1 Fill in Lot 8 - Level 1 Fill in Lot 4

  • Civil Works - Hydraulics – Sewer Structures in Lots 1 - Hydraulics – Stormwater structures in Lot 1 - Hydraulics – Water mains in Lot 1 - Common Service Trench – Lot 1 - Road Construction - Discovery St (east side towards Monaro Cr)


Works ahead over next month (April 2020)


  • ACM remediation works - Lot 8 - Trench chasing in Lot 8

  • Earthworks - Level 1 fill in Lot 4 - Level 1 fill in Lot 8 - Level 1 fill in Lot 7 - Level 1 fill in Lot 2 - General earthworks in Lot 5 - Excess material removal from site.

  • Civil Works - Hydraulics – Sewer Works in Lot 2, 3, & 4 - Hydraulics – Temporary above ground sewer works in Lot 3 & 4 - Hydraulics – Stormwater Lot 3 & 4 - Hydraulics – Water Lots 2 & 3 - Common Services Trenches – Lots 2, 3 & 4 - Road Construction – Cimba Lane, Discovery St, Aviemore Lane & Cygnet Crescent - Footpath – Discovery St

  • Landscaping - Preparation works in Lots 4 & 5

Potential Changes to Traffic Pedestrian Changes etc

  • Monaro road closed between Discovery St and Cygnet Crescent

  • Discovery Street closed up to the Display Village

  • Norfolk St closed

  • Stop & Go Traffic Control on Cygnet Crescent / Endeavour Street

  • Temporary footpaths - Monaro Crescent - Cygnet Crescent - Endeavour St

Community / Environmental / WHS

  • Stakeholder Notice Board - Notice board to advise Red Hill community of project weekly updates - Key project changes including traffic management updates to be include on the Notice Board at the Shopping Centre

  • Dust Management - Water spray dust suppression in work areas

  • Vibration Monitoring - Vibration monitoring reports produced weekly

  • Noise Management - All noisy activities to be managed in line with the TCCS guidelines - Prior notification of residents of excessive noise activities to be made

  • Contractor Parking - All parking sites for contractors are within the site boundary - Contractors to notified during induction / weekly meetings to park within dedicated zones

  • UAV Surveys - Drone flights used only for daily site surveys (volumetric calculations, progress photos, stockpile management and progress tracking) - Drone flight managed in line with CASA guidelines - Flights conducted to be conducted only after 7am.

Thank you again for your patience in 2020 as we progress this project.

0 views

© 2018 Stockland and DOMA
 

COMMUNITY ENQUIRIES
1800 909 773

info@theparksredhillcommunity.com.au

Disclaimer: This website is supplied for the purpose of providing an impression of The Parks, Red Hill and the approximate location of existing and proposed third party infrastructure, facilities, amenities, services and destinations, and is not intended to be used for any other purpose. All details, images and statements are based on the intention of, and information available to, Stockland and DOMA as at the time of publication (November 2018) and may change due to future circumstances.