January works update

Works completed over prior month(s) (January 2020)

  • ACM remediation works o Lot 8 o Lot 1 sediment pond walls o Remediation works in Lot 6

  • Lot 1 Verges Along Cygnet Cr, Lady Nelson Pl & Monaro Cr

  • Earthworks o Level 1 fill in Lot 4 (Area between Walter Hood Cr & Beagle St) o Level 1 Fill in Lot 8

  • Civil Works o Hydraulics – Sewer Works in Lot 1 o Stormwater Tank base slab

  • Offsite Works o La Perouse St / Monaro Cr Roundabout upgrade o La Perouse St island upgrade o Monaro Cr island upgrade


Works ahead over next month (February 2020)

  • ACM remediation works o Lot 8 completion o Trench chasing in Lot 4 o Lot 1 Verges Along Cygnet Cr, Lady Nelson Pl & Monaro Cr o Lot 2 Topsoil Disposal o Lot 1 Verge Along Discovery St o Lot 2 remediation o Lot 5 – Tree areas o Lot 4 Verges

  • Earthworks o Level 1 fill in Lot 4 o Level 1 fill in Lot 8 o Level 1 fill in Lot 6 o Level 1 fill in Lot 2

  • Civil Works o Hydraulics – Sewer Works in Lot 1 o Hydraulics – Stormwater Lot 1 o Hydraulics – Water Lot 1 o Stormwater Tank o Hydraulics – Sewer Works in Lot 4


Potential Changes to Traffic Pedestrian Changes etc

  • Monaro road partial closure between Discovery St and Cygnet Crescent

  • Discovery Street Closure

  • Temporary footpaths o Monaro Crescent o Cygnet Crescent o Endeavour St


Community / Environmental / WHS

  • Stakeholder Notice Board o Weekly updates ongoing

  • Dust Management / Stockpile management o Dust suppression systems including polymer coating / water suppression (ongoing)

  • Vibration Monitoring (ongoing)

  • Noise Management o All noisy activities to be managed in line with the TCCS guidelines o Prior notification of residents of excessive noise activities to be made

  • Contractor Parking o All parking sites for contractors are within the site boundary o Contractors to notified during induction / weekly meetings to park within dedicated zones

  • UAV Surveys o Drone flights used only for daily site surveys (volumetric calculations, progress photos, stockpile management and progress tracking) o Drone flight managed in line with CASA guidelines o Flights conducted to be conducted only after 7am


Thank you again for your patience in 2020 as we progress this project.

10 views

© 2018 Stockland and DOMA
 

COMMUNITY ENQUIRIES
1800 909 773

info@theparksredhillcommunity.com.au

Disclaimer: This website is supplied for the purpose of providing an impression of The Parks, Red Hill and the approximate location of existing and proposed third party infrastructure, facilities, amenities, services and destinations, and is not intended to be used for any other purpose. All details, images and statements are based on the intention of, and information available to, Stockland and DOMA as at the time of publication (November 2018) and may change due to future circumstances.