January works update

Works completed over prior month(s) (January 2020)

  • ACM remediation works o Lot 8 o Lot 1 sediment pond walls o Remediation works in Lot 6

  • Lot 1 Verges Along Cygnet Cr, Lady Nelson Pl & Monaro Cr

  • Earthworks o Level 1 fill in Lot 4 (Area between Walter Hood Cr & Beagle St) o Level 1 Fill in Lot 8

  • Civil Works o Hydraulics – Sewer Works in Lot 1 o Stormwater Tank base slab

  • Offsite Works o La Perouse St / Monaro Cr Roundabout upgrade o La Perouse St island upgrade o Monaro Cr island upgrade


Works ahead over next month (February 2020)

  • ACM remediation works o Lot 8 completion o Trench chasing in Lot 4 o Lot 1 Verges Along Cygnet Cr, Lady Nelson Pl & Monaro Cr o Lot 2 Topsoil Disposal o Lot 1 Verge Along Discovery St o Lot 2 remediation o Lot 5 – Tree areas o Lot 4 Verges

  • Earthworks o Level 1 fill in Lot 4 o Level 1 fill in Lot 8 o Level 1 fill in Lot 6 o Level 1 fill in Lot 2

  • Civil Works o Hydraulics – Sewer Works in Lot 1 o Hydraulics – Stormwater Lot 1 o Hydraulics – Water Lot 1 o Stormwater Tank o Hydraulics – Sewer Works in Lot 4


Potential Changes to Traffic Pedestrian Changes etc

  • Monaro road partial closure between Discovery St and Cygnet Crescent

  • Discovery Street Closure

  • Temporary footpaths o Monaro Crescent o Cygnet Crescent o Endeavour St


Community / Environmental / WHS

  • Stakeholder Notice Board o Weekly updates ongoing

  • Dust Management / Stockpile management o Dust suppression systems including polymer coating / water suppression (ongoing)

  • Vibration Monitoring (ongoing)

  • Noise Management o All noisy activities to be managed in line with the TCCS guidelines o Prior notification of residents of excessive noise activities to be made

  • Contractor Parking o All parking sites for contractors are within the site boundary o Contractors to notified during induction / weekly meetings to park within dedicated zones

  • UAV Surveys o Drone flights used only for daily site surveys (volumetric calculations, progress photos, stockpile management and progress tracking) o Drone flight managed in line with CASA guidelines o Flights conducted to be conducted only after 7am


Thank you again for your patience in 2020 as we progress this project.